Mining & Natural Resources — Equipment & Maintenance

Track how much the fleet is available and used, keep maintenance on schedule, categorise breakdowns, post fuel and consumables against Warehouse stock and watch component life.

What this group covers

Five screens for the equipment and maintenance team. Equipment itself is defined in Operational Setup (Equipment & Fleet Registry); this group records what happens to it. This is separate from the core Maintenance module, which stays the place for general asset work — here everything is about mining machines, their hours and their components.

ScreenRecordsVerified or approved by
Equipment Availability & UtilizationShift hour logs and the KPI dashboardMine Manager verifies logs
Preventive Maintenance ScheduleMaintenance tasks by hours, kilometres or calendar days—
Breakdown & Downtime TrackingBreakdowns, reasons, downtime and production lostMine Manager closes events
Fuel & Consumables ManagementFuel, lubricant, tyre and parts consumption—
Component LifecycleEngines, transmissions, buckets and their replacements—

Equipment Availability & Utilization

Log the hours of each machine per shift: scheduled, operating, standby, planned maintenance and breakdown. The hours of a log cannot exceed the scheduled hours, and there is one log per machine, date and shift. The KPI dashboard counts only logs a manager has verified, sums the hours first and then takes the ratios on the totals.

KPIFormula
Availability(Scheduled − Planned maintenance − Breakdown) ÷ Scheduled
UtilizationOperating ÷ (Scheduled − Planned maintenance − Breakdown)
Effective utilizationOperating ÷ Scheduled

Choose the date range on the dashboard; the fleet total is shown under the machines.

Preventive Maintenance Schedule

A task is due by operating hours, kilometres or calendar days. For hours and kilometres the screen calculates the next due reading (last service + interval) and the remaining distance to it; for calendar tasks it counts the days to the due date. Update the meter on a task as the machine works; once it passes its limit, or the due date has passed, the task shows as overdue. Starting and completing a task records who did it; completing asks for the service meter and the labour hours and automatically schedules the next task from the reading it was done at.

Breakdown & Downtime Tracking

A breakdown goes Reported → In repair → Restored → Closed (or Cancelled with a reason). Every breakdown has a reason category so the causes can be compared.

  • Engine
  • Transmission
  • Hydraulic
  • Electrical
  • Tyre
  • Structural
  • Operator error
  • Fuel supply
  • Weather
  • Other

Restoring the machine asks for the downtime in hours. With the production rate lost per hour and the value per tonne, the screen calculates the operational loss: tonnes lost = downtime hours × rate, and value lost = tonnes lost × value per tonne. The By reason tab totals events, downtime and production lost per category.

Fuel & Consumables Management

A consumption line records an issue of diesel, lubricant, tyres, parts or filters to a machine. Link it to a core Warehouse item and posting deducts the quantity from that item’s stock and writes a stock movement; voiding a posted line (with a reason) gives the stock back. If the Warehouse does not hold enough, the post is refused and nothing changes. The Open Purchase button takes you to the core Purchase module to reorder.

Stock lives in Warehouse

This screen never keeps its own stock. The Warehouse item is the single source; posting and voiding only move its quantity and leave a movement behind.

Component Lifecycle

Record each major component fitted to a machine with its install reading and expected life in hours. Update its meter as the machine works and the screen shows the life used, the percentage of expected life, the remaining hours and an estimate of the days left (remaining hours ÷ average hours per day). Replacing a component asks for the reading at removal and a reason; the Replacement history tab lists replaced components with the life each one achieved, and a new component can point at the one it replaced. Every step is kept in the change history.

Frequently Asked Questions

Why is a shift not in the KPI dashboard?
Only verified logs are counted. Ask a manager to verify it.
Why was my fuel posting refused?
The linked Warehouse item does not hold that quantity. Reduce the quantity or reorder in Purchase.
Where do general asset repairs go?
The core Maintenance module. This group is for mining machines and their hours, breakdowns and components.
How is the remaining life estimated?
Expected life minus hours used, divided by the average hours the machine runs per day.